The first sewage treatment plant in the Middle East with polyurea as an inner lining

As the specifications called for a GRP liner, several discussions were held with Dubai Municipality to change the liner from GRP to polyurea. As a result, our technology has increased the quality and performance of the project and minimized the execution time. The material was supplied by VIP-Delta Co., the former distributor of the VIP product range in the UAE.

  1. The concrete has been pressure washed and cleaned of any residue that could impair adhesion
  2. QuickFill and QuickPrime Epoxy were applied as a primer prior to spraying
  3. The Polyurea QuickSpray Industrials was applied with a layer thickness of 2.5 mm using the Graco XP-2 high-pressure spray unit
  4. The whole process of surface preparation and application of the primer was successfully completed within 4 months despite extreme conditions in the underground tunnel infrastructure
Reference profile

Reference profile

Polyurea lining of a sewage treatment plant

Dubai

UAE

2020

90.000 m²

Aecom

Deltachem

pictures from the project

VIP systems in this project

LIQUISHIELD

LIQUISHIELD is designed to meet the growing demand from consulting engineers for complete system solutions as opposed to products the LIQUISHIELD systems make it easy for consulting engineers to specify a complete liquid containment solution from one manufacturer. The LIQUISHIELD range covers primary and secondary containment of chemical liquids, abrasive slurries as well as drinking water.
SYSTEMS

QUICK REQUEST

VIP WORLDWIDE

Find your contact now!