GEMS Saudi handles waste water recycling for major Oil & Gas companies in the region. The concrete tanks were lined with a non VIP polyurea six months back and had drastically failed due to the inexperience of the applicator overlooking the overcoat windows. VIP was called in for an appropriate and immediate rectification. GEMS wanted to carry out in house applications so VIP trained GEMS as an approved applicator.
The entire rehabilitation of 4,000 sqm was carried out in one month and the recycling plant is recommissioned successfully.
Application steps:
1) Surface preperation
2) Priming
3) Application of 3mm QuickSpray Industrial- hot spray applied.